Fearing more stone blockage
Store Norske most likely will need to do extra drilling in Lunckefjell to clarify if there is stone blockage of the coal.
Eirik Palm
On June 19, the company announced it will need to halt development of the first stope panel in the ecotone zone and the panel will therefore be 216 meters shorter than planned. This amounts to a production loss of 128,000 tons of coal, equivalent to 6.5 percent of the normal annual production for Store Norse. The value of this coal depends on market prices, but at 80 dollars per ton would amount to about 61 million kroner.
Considerations
Along with geologists and rock engineers, Managing Director Per Andersson had a full examination before the decision. Now the company is considering drilling extra holes to avoid more surprises.
"It's not a pleasant surprise that we have to deviate from the plan and must leave the coal, that none of us likes," he said. "At the same time, this is a panel in the outer part of the field and there will always be some uncertainty as to the actual conditions in the mountain compared to what core drilling has told us."
1 måned digitalt abonnement
Digital måned
10,- den første måneden, deretter 203,- per måned
for 1 måned
Bestill her
1 år papir og digitalt abonnement
Komplett HELÅR.
2138,-
for 12 måneder
Bestill her
6 måneder papir og digitalt abonnement
Komplett halvår.
1215,-
for 6 måneder
Bestill her
1 år digitalt abonnement
Digitalt helår
1600,-
for 12 måneder.
Bestill her
6 måneder digitalt abonnement
Digitalt halvår
950,-
for 6 måneder
Bestill her
1 år komplett sør for Bodø
2578,-
Full digital tilgang, eAvis og papirutgaven én gang i uken.
Portotillegg pr. avis fra Bodø og sørover pålydende kr 10,-
Bestill her
6 måneder komplett sør for Bodø
1435,-
Full digital tilgang, eAvis og papirutgaven én gang i uken.
Portotillegg pr. avis fra Bodø og sørover pålydende kr 10,-
Bestill her